What Nvidia and xAI said on October 28, 2024

Nvidia said xAI and Nvidia built the Colossus cluster in Memphis in 122 days, starting with 100,000 Nvidia Hopper GPUs on Spectrum-X Ethernet networking, and that xAI planned to double it to 200,000 GPUs.

Confirmed On the record from the person or company named.

Source
Nvidia
Status
Confirmed
As of

The claim, in our words

This is our summary of what Nvidia and xAI said or was reported to say, not a quote. The exact words are at the source.

See it on the full timeline →

Timeline

More from the timeline

Full timeline
  1. Elon Musk Reported

    Said in a reply on X that the cost of serving Grok Bot was unsustainably high relative to revenue. Users were reported to be running out of weekly allowances days early; no cost figure was given and the report does not say whether allowances were cut.

  2. Anthropic Reported

    Anthropic's IPO filing was reported to say it expects to pay about $3.1 billion a month once all contracted SpaceX compute is delivered, expected by the end of 2026, with either side able to cancel on 90 days' notice after early 2027.

  3. SpaceX Expected

    SpaceX disclosed in an SEC filing a roughly $40 billion, five-year deal with Apollo Global Management for Nvidia Vera Rubin GPUs, to be made available gradually from the first half of 2027. The contract was not yet final.